31-10-2017
Work is underway on the external finishing of the new building of the A. M. Qattan Foundation (AMQF) in the Al-Tira neighbourhood, Ramallah. Aluminium beams were installed around the main building. Glass panels were fixed on the northern and southern facades. Work is underway to install stone slabs on outer walls and prepare the car entrance.
Internal finishing works have already started. Plasterboards, insulation panels, tiles and ceilings are being fixed. Work is in progress to install lift infrastructure and HVAC systems.