The New Building Project: Work Progress

Home In Qattan News The New Building Project: Work Progress

 

Work is underway on the external and internal finishing of the new building of the A. M. Qattan Foundation (AMQF) in the Al-Tira neighbourhood, Ramallah. Work has started to install metal beams on the outer facades of the building.

 

80% of stone slabs on outer walls have been installed. 90% of the work involving the installation of glass and aluminium panels has been completed.

 

Work has been also initiated to finish office ceilings. The ceilings and walls of exhibition halls have been finished. Floor tiling and construction of outer walls have been completed as well.